For decades, a fieldstone house off Frankston Highway handled the messages for its part of Tyler. T.B. and Gladys Stewart once had the only phone in the neighborhood, the Tyler Morning Telegraph reported in 2016. People who came to town looking for work left the Stewarts' number. When an employer called, someone would flag down a wagon on Highway 155 to pass the word along.
The couple gave that house and its nine acres to the City of Tyler in 2012 so the land could become a park. Fourteen years later, crews are still building it. For most of those years the donation had no reliable funding source. It sat waiting until the city ran a concrete trail right past its front door. The trail opened in January. The park is scheduled for this winter. If you want to see the site before the ribbon-cutting, you can already walk there.
A Donation That Kept Missing Its Funding
The 2016 plan was ambitious. The Telegraph described a master plan with a pond for irrigation, a community garden, a picnic area, a playground, parking, and the reuse of the Stewarts' 1,000-square-foot house. The site would also be the starting point of a self-guided African American History Tour. The cost estimate was $1.2 million. It then grew by $400,000 to cover asbestos abatement and water infrastructure upgrades. The money was supposed to come from hotel-motel tax revenue, which also had to cover other large projects, including the city's proposed hotel conference center.
"I wish we had more money," Stephanie Franklin, then the city's managing director of culture, recreation and tourism, told the Telegraph. The city had applied for two grants and hadn't won either one. Officials said it would "realistically" be years before the project was done.
They were right. Here is how the years went:
- 2012: The Stewart family donates nine acres on Highway 155.
- 2016: The city budgets $300,000 for a first phase and says the full project will take years.
- July 2024: The city moves to seek a roughly $500,000 matching grant. The parks director tells the Telegraph that "parks have just been underfunded for a very long time."
- February and March 2025: A community meeting presents the proposed amenities, and the council approves a $67,500 design contract with MHS Planning & Design.
- January 2026: Legacy Trail Phase II opens, starting at the future park site.
- June 23, 2026: Groundbreaking.
- August 12, 2026: The City Council awards the construction contract.
The last four entries all fall within about 18 months. The trail opened at the park's front edge in January 2026, and the groundbreaking and construction contract followed within eight months.
The Trail Turned a Stalled Lot Into a Trailhead
Parks Director Leanne Robinette explained the timing to the Tyler Morning Telegraph in April: "The thought of it came to fruition a few years ago when we knew the Legacy trail was going to start here. We actually started planning for it in the last year."
The trail had money the park never had. KLTV reported that a TxDOT grant paid 80% of the $2.9 million trail project, with the city's half-cent sales tax covering the rest. CBS19 put the cost at roughly $2.7 million and said construction took nearly two years. Once the city had paid for that much concrete leading to the Stewart property, a smaller project at the end of it was much easier to fund.
The park itself is also paid for differently now. At the August 12 council meeting, Robinette presented a $295,000 bid from Schumacher Construction, the lowest of seven bidders. With the playground and restroom contracts approved earlier, Stewart Park's total came to about $630,000. That money comes from the Keep Tyler Beautiful Capital Improvement account, which is funded by landfill dumping fees. She called the bid "the final puzzle piece for Stewart Park" and said it comes at no cost to residents.
So a project that once needed $1.6 million from a competitive tax fund is being built for about $630,000 from a dedicated fee account. The scope is smaller too, as the next section shows.
Walking It Today, South to North
The trail runs from the future park north to Peete Elementary. The city's parks department lists it as 2 miles of 12-foot-wide concrete. CBS19 measured the new section at about 1.7 miles. Going north, you'll pass:
- The Stewart Park trailhead at 2713 Frankston Highway, near Earl Campbell Parkway. KLTV gave this as the trail's access address. Construction fencing should be expected here until the park opens.
- The Frankston Highway and Old Noonday Road stretch. The path follows Frankston Highway north and then Old Noonday Road.
- W.E. Winters Park at 910 S. Peach Ave. This is the park formerly called Peach Park. It reopened in June 2025 after a yearlong renovation, and the trail runs right through it. The city lists a pavilion, playground, restrooms, basketball and multipurpose courts, picnic areas, and a 0.4-mile concrete walking loop. It's open sunrise to sunset. CBS19's reopening coverage also mentioned a bridge, new benches and picnic tables, and a pollinator-themed mural.
- Peete Elementary, the north end of the trail. Parks and Rec does not list parking at this end.
The trail had regular users before it officially opened. "A lot of people are walking through Winters Park to get their kids," Robinette told KLTV at the January ribbon-cutting.
Parking is the one detail still unclear. The parks department lists two parking areas for this section, at the Stewart trailhead and at W.E. Winters Park. At the June groundbreaking, though, parks services coordinator Kristi Baker told the Telegraph that the city "does not plan to expand parking near the park." For now, the surest place to park is the lot at W.E. Winters, near the middle of the route.
What's Going Up at 2713 Frankston Highway
The Stewart Park being built today is a smaller, trail-focused version of the 2016 plan, as the table below shows:
Element | 2016 master plan | 2026 plan |
|---|---|---|
The Stewart home | 1,000-square-foot house reused in the park | House can't be saved structurally; its stone used throughout the park |
Water feature | Pond for irrigation | None listed |
Gardens | Community garden | None listed |
Play and gathering | Playground, picnic area | Playground, pavilion, picnic tables, restroom |
Learning | Local history walking tour; start of the African American History Tour | Outdoor learning area with a small stage, history signage, historical marker |
Trail | Walking trail | Nature trail and trailhead for Legacy Trail Phase II |
Estimated cost | $1.6 million | About $630,000 |
The house is the biggest change. "Although the home cannot be structurally preserved, its presence will still be honored in the park design through the use of stone which will be incorporated throughout the park," Councilwoman Petra Hawkins said at the groundbreaking, according to the Telegraph. The same report noted that the Stewarts were together for 83 years and were longtime residents of the historic St. Louis community. Their home was among the first in the area with electricity, water, gas and telephone service, and it became a place where neighbors gathered. The 2016 article described St. Louis as a farming community on both sides of present-day Frankston Highway, extending south of Loop 323, that was annexed into Tyler in the late 1970s.
The small stage fits who the Stewarts were. Hawkins said the family "had a heart for philanthropy and education," and the city plans to use the outdoor learning area for school presentations and community events.
When it opens, Stewart Park will be the City of Tyler's 29th park and its first new one since September 2004.
The Opening Date, and the Missing Link
The city's project page says construction will continue through the end of the year, followed by a grand opening in "Winter 2026." No exact date has been announced, and the parks department's listing still says "Development in progress." In June, Baker said the schedule depends on weather, material availability and any construction delays.
The trail's longer future also depends on outside money. Legacy Trail Phase I, the 4.5-mile path on the old Cotton Belt rail line along Old Jacksonville Highway, opened in July 2019 and runs toward Flint. Phase III would connect the two sections. On the city's project tracker, its dates are "to be determined depending on grants." KLTV reported in January that there was no timeline for the connection. For now, Phase II is a separate 2-mile route between Frankston Highway and Peete Elementary, with a renovated park in the middle and a new one being built at its south end.
If you live near the Frankston Highway corridor and want to know how a new trailhead park might figure into your home's value, The Crutcher & Hartley Team can walk you through it. Request a Free Home Valuation.